10th Avenue Bridge Update

PW project updates

10th Ave Bridge Rehab and Watermain Project

June 18, 2021

10th Ave Bridge and Watermain Project

This project will rehabilitate the historic 10th Ave SE bridge over the Mississippi River and W River Pkwy. A new water main will be installed under the river as part of the project.


Latest Project News

Construction Update Meeting - Friday, June 25, 2021 at 10:30 am

Project staff will hold a virtual construction update meeting next Friday using GoTo Meeting. Members of the public are invited to join the online meeting and hear updates on construction progress and speak with project staff.

Please use this link to join the 10th Ave Bridge Online Construction Update Meeting from your computer, tablet or smartphone:

https://global.gotomeeting.com/join/784924461

You can also dial in using your phone.

United States: +1 (224) 501-3412  Access Code: 784-924-461  

The bridge was closed on March 30th, 2020 and the contractor has been actively working on repairs. For more details on the repairs, schedule and bridge deck changes, please see the latest Construction Update or go to the project page 10thavebridge.com


What's Coming Up

The 10th Ave Bridge will remain closed to all traffic including, vehicles, bikes, and pedestrians until fall 2021.

West River Parkway (roadway only) will be closed to motor vehicles through April 2021. The adjacent trail will remain open for bicyclists and pedestrians.

Work requires the use of heavy equipment that will increase noise, vibration, and dust
in work areas.

Access to adjacent apartments and businesses will remain open during the construction activity.


For more information on this project contact: 

Bridge Contact: Meseret Wolana, [email protected] or 612-673-3527

Water Main Contact: Shahin Rezania, [email protected]

10thavebridge.com